How long does it take to build a website?

Updated 7 min read

Person writing notes on a large desk calendar
Photo: RDNE Stock project / Pexels
On this page
  1. Typical website timelines by who builds it
  2. What actually takes the time
  3. What a realistic 10-day build looks like
  4. How to speed up any website project
  5. Live is not the same as found
  6. Which route is fastest for you?
  7. Common questions

A simple small-business website takes anywhere from a few days on a do-it-yourself builder to two to six weeks with a freelancer, and an agency project often runs five months or more. Much of that time goes to words, photos, decisions and feedback, so the owner has more control over the schedule than most people expect.

Here is what the published timelines say, where the time really goes, and what a fast, realistic build looks like day by day.

  • 20–60 hoursBuilding your first site yourselfdotCanada, Oct 2025
  • 2–6 weeksA standard site with a freelancerUpwork, Nov 2026
  • 7 monthsTypical web design project reviewed on ClutchClutch, Sept 2026

Typical website timelines by who builds it

Doing it yourself. Sources disagree here because they count different things. GoDaddy’s Canadian guide says a builder lets you create a site “in a matter of hours or days”. HubSpot puts do-it-yourself development at one to two weeks. dotCanada counts the work itself at 20 to 60 hours for a first site. At ten hours a week, that’s two to six weeks. Squarespace gives you 14 days free before you pay, which makes a handy deadline for a first draft, and Wix lets you build for free and pick a plan when you’re ready to publish on your own domain.

A freelancer. Upwork says a standard site often takes two to six weeks, and complex or more custom builds three to six months.

A studio or agency. HubSpot says designing and launching a professionally built website could take five to six months. Clutch, which collects client reviews of agencies, says most web design projects reviewed on its site last seven months.

Typical time to launch, upper end of each range, in weeks
Do it yourself on a builder1–2 weeks
Freelancer, standard site2–6 weeks
Freelancer, complex or custom build3–6 months
Professional firm5–6 months
Typical project reviewed on Clutch7 months
Source: HubSpot (updated May 2025), Upwork and Clutch (2026)

Those agency months aren’t wasted. A big project has more pages, more people signing off and more testing. A five-page site for a local business has far less of all three, which is why it can move much faster.

What actually takes the time

On a small site, these are the jobs that tend to stretch the schedule, and most of them sit with the owner.

Writing the words

Nobody can describe your services, prices and service area better than you, and that makes you the bottleneck. Writing about your own business is harder than it sounds, so start before you hire anyone. Rough notes are fine; a good designer or writer can shape them.

A small business site usually needs a home page, a page for each main service, an about page and a contact page. Start with the services page. Write down the questions customers ask you on the phone and answer them in plain sentences, with prices or price ranges if you can share them. That one page often becomes the backbone of the whole site.

Getting photos

Real photos of your shop, your team and your work make a site feel trustworthy, but they need planning. Booking a photographer, tidying the space or waiting for good light can add days. Free stock photos fill gaps while you wait.

Woman photographing gift bags and shoes set up on boxes by a window
Photos are often the last thing to arrive. Shoot them early, even on a phone.Photo: PNW Production / Pexels

Decisions and feedback rounds

HubSpot warns that you should expect two to three weeks of emails and mockup versions before you settle on an approved design, and another one to two weeks for review and revision near the end. Every extra person who has to approve the design adds to that.

Feedback goes faster when it arrives in one list from one person. Ten emails with one change each, from three people who disagree, can turn a two-day review into two weeks.

Booking and payment tools

If customers will book or pay online, someone has to enter every service, price, staff member, opening hour and cancellation rule. Payment providers also ask for business and bank details before they pay out. Open those accounts early, so the setup doesn’t wait on paperwork in launch week.

Domain, email and your Google listing

Pointing your domain at a new site, or moving email, means changing DNS records. Google’s own help says DNS changes are usually processed within 48 hours, and sometimes take up to 72. If you want a .ca, you need to meet CIRA’s Canadian presence requirements, which citizens, permanent residents and Canadian corporations do. Your Google Business Profile has its own verification steps; our guide to adding your business to Google Maps walks through them.

What a realistic 10-day build looks like

A small site can be designed, built and launched in ten days when the scope is fixed and the owner can reply quickly. It’s the schedule we use for our own fixed-price sites, and it looks like this.

  1. 1

    Day 0: The brief

    You describe what you sell, who buys it, where you work, the pages you need and a few sites you like. Send your logo, photos and any rough notes you have.

  2. 2

    Day 2: The homepage mockup

    A designed homepage arrives within 48 hours, with your own words and photos where possible. Reacting to something real is far quicker than describing it.

  3. 3

    Day 3: One round of feedback and the deposit

    You send one list of changes, agree the final page list and pay the deposit. From here the scope is fixed.

  4. 4

    Days 3 to 7: The build

    The other pages, contact or booking forms, payments if you need them, phone layouts, page titles and your Google listing details are built and connected. Domain and email settings get checked early, because DNS changes can take up to 48 hours to settle.

  5. 5

    Day 8: Your review

    You click through every page on your phone and laptop and send a single list of fixes.

  6. 6

    Day 9: Fixes and final checks

    Changes go in, every form is tested by sending a real message, and the domain is ready to switch over.

  7. 7

    Day 10: Live

    The site goes live, old addresses redirect to the right new pages, and the site is submitted to Google.

Hand-drawn wireframe sketches of web pages on paper
A homepage mockup early on turns vague ideas into specific feedback, which is what keeps a short schedule short.Photo: picjumbo.com / Pexels

Ten days only works with limits. It needs five or so pages, words and photos that are ready or quick to gather, and one person who makes decisions. An online store with hundreds of products, or a site that needs sign-off from a board, belongs on a longer schedule, and that’s fine.

How to speed up any website project

These steps help whether you build it yourself, hire a freelancer or work with an agency.

Before you start
  • Write a one-page brief covering what you sell, who buys it, where you work and three websites you like.
  • Put your logo, photos, prices, hours and list of services in one shared folder.
  • Choose one person who makes the final call, and agree how quickly they will reply.
  • Get the page list and the number of feedback rounds in writing.
  • Check that you can log in to your domain account well before launch week.
  • Launch with the pages you have ready and add the rest afterwards.

The last point matters most. A clear five-page site that’s live this month does more for you than a perfect fifteen-page site that’s still in review in the spring.

Live is not the same as found

Launch day is when Google can start finding the site, and that takes time too. Google says that after you ask it to recrawl your pages, crawling can take anywhere from a few days to a few weeks. Submitting a sitemap in Search Console on launch day is the usual way to ask. If you’re replacing an old site, redirect the old page addresses to the new ones so the visitors and links you already have don’t land on an error page.

Which route is fastest for you?

If you have more time than money, a builder gets you online fastest, and our comparison of Wix, Squarespace and a custom site will help you pick one. Block out the hours in your calendar the way you would for a job, because evenings have a way of filling up.

If you’d rather hand the work over, ask every freelancer or studio for a written schedule with dates, and ask what they need from you to hit it. A good answer names specific things, like your logo files, a page list and a feedback deadline. A vague answer usually means the schedule is vague too. To weigh speed against price, our guide to what a website costs in Canada has the numbers.

Common questions

How long does it take to build a small business website?

Doing it yourself on a builder takes a few days to two weeks, and dotCanada puts a first site at 20 to 60 hours of work. With a freelancer, Upwork says a standard site often takes two to six weeks. Agency projects commonly run several months.

Can a website be built in a week or two?

A small site can, if the page list is fixed, the words and photos are ready and one person gives quick feedback. Online stores, large sites and projects with many decision-makers take longer.

What slows a website project down the most?

Usually the work around the build: writing the words, getting photos, making decisions and waiting on feedback. HubSpot says the design back-and-forth alone often takes two to three weeks.

How long does it take for a domain to point to a new website?

Pointing a domain at a new website or email means changing its DNS records. Google says DNS changes usually take effect within 48 hours and sometimes take up to 72, so make the change a few days before launch.

Why do agencies take months?

Bigger projects have more pages, more people signing off and more rounds of revisions. HubSpot puts a professionally built site at five to six months, and Clutch says most web design projects reviewed on its site last seven months.